Math, asked by sonu2034, 1 year ago

If 5 men can do a piece of work in 28 days,then the number of persons to do the same work in 7 days is.
step \: by \: step \: answer

Answers

Answered by bhagyashreechowdhury
2

Given:

5 men can do a piece of work in 28 days

To find:

The number of persons to do the same work in 7 days

Solution:

Let's assume "x" represents the no. of persons who can do the same piece of work in 7 days.

Since the total amount of work done by 5 men and "x" no. of persons is same, therefore we can use the Man-Days formula to solve the given problem:

\boxed{\bold{M_1 \times D_1 = M_2 \times D_2}}

Here we have,

M₁ = 5 mens

D₁ = 28 days

M₂ = x persons

D₂ = 7 days

Now, on substituting the given values in the formula above, we get

5 \times 28 = x \times 7

\implies  140  = x  \times 7

\implies x = \frac{140}{7}

\implies \bold{x = 20}

Thus, the number of persons to do the same work in 7 days is → 20.

--------------------------------------------------------------------------------------------

Also View:

If 20 persons can do a piece of work in 7 days then the number of persons required to complete the work in 28 days is?

https://brainly.in/question/11791156

If 4 men and 5 women can do a piece of work in 50 days whereas 7 men and 13 women can do the same piece of work in 28 days, how long will 10 men and 6 women take to do the same piece of work?

https://brainly.in/question/12149578

If 12 men can do a piece of work in 24 days, then in How many days can 18 men do the same work?

https://brainly.in/question/6475644

Answered by pavankrishnareddymar
2

Answer:

20

Step-by-step explanation:

5 men - 28 days

? men - 7 days

men will become more

so, more by less

28/7 × 5

5 × 4 = 20

∴ 20 men are required to complete the work in 7 days