If 5 more men are added, how long will it take to complete same piece of work?
Answers
Answer:
Given:-
15 men can do a piece of work in 80 days.
To Find:-
If 5 more men are added, how long will it take to complete same piece of work?
Concept Used:-
Direct Proportion
Solution:-
Let the number of days taken after adding 5 more men be x.
According to question,
\sf :\implies\:\dfrac{15}{20}=\dfrac{x}{80}:⟹
20
15
=
80
x
On Cross Multiplication,
\:20x=80\times15:⟹20x=80×15
\\:20x=1200:⟹20x=1200
\\:x=\dfrac{1200}{20}:⟹x=
20
1200
=\dfrac{120}{2
:⟹x= 2 =120
:x=60:⟹x=60
Hence, 60 days will be taken to complete a piece of work after adding 5 more men.
━━━━━━━━━━━━━━━━━━━━━━━━━
Answer:
60 days
Step-by-step explanation:
Let the number of days taken after adding 5 more men be x. Hence, 60 days will be taken to complete a piece of work after adding 5 more men