Math, asked by Rucha101, 1 year ago

if 55 men can do a piece of work in 42 days. how many mens will do it in 14 days (using direct and inverse) ​

Answers

Answered by riya7583
2

let \: the \:number \: of \: men \: be \: x \\ x = 55 \times 42 \div 14 \\ x = 165men

Answered by PSN03
1

52 men=42 days

1 man=1/42 days

x men=14 days          (actually x men ,sounds cool LOL)

x=42*1/14*55

=3*55

=165

plz mark as brainliest