IF 56 men can do a piece of work in 42days how many men will do it in 14 days
Answers
Answered by
1
Answer:
168 men
Step-by-step explanation:
Work can be done in 42 days by = 56 men
In 1 day it can be done by = (56×42) men
In 14 days it can be done by = [(56×42)/14] men
= 168 men(Ans)