if 56 men can do a work in 84 days. How many men will do it in 28 days
Answers
Answered by
0
Answer:
jauwhshshhwwjuwnwjjwjw
Answered by
0
Answer:
56 men = 84 days
X men = 28 days
Here we want how many men will do the work in 28 days.....
So, let us take that no. of men do work in 28days =x
To get the value of x we should do cross multiplication.
X= 56 × 28 ÷ 84
X = 1568 /84
X= 18.66( approx) or 19
X = 19 men