if 6 man can do a piece of work in 30 days of 9 hours each, how many men will take to do 10 times the amount of work if they work 25 days of 8 hour each
Answers
Answered by
0
Answer:
6×30×9=25×8×x/10
x= 6×30×9×10/25×8
x= 81 man