Math, asked by ayushseth3147, 10 months ago

If 6 men can do a work in 32 days in how many days will 24 men complete the same work

Answers

Answered by priyankarikpaul
19

Answer:

8 days

Step-by-step explanation:

6 men take 32 days

1 man will take 32 * 6 days= 192 days

24 men will take 192/24 days = 8 days