If 6 men completes the work in 15 days then how many men are required to finish the work in 10 days?
Answers
Answered by
0
Answer:
15 days required to finish the work for 6 men
1 day required to finish the work for 6×15 men
10 days required to finish the work for
6×15/10 men
=9 men
so 9 men required to finish the work in 10 days