Math, asked by angammeitei, 4 days ago

If 6 men take 4 days to complete a job, how many days will 12 men take - (a) 2 (b) 3 (c) -2 (d) -3​

Answers

Answered by subhamtanti
3

the answer is 8

Step-by-step explanation:

4×2=8 hope it helps

Answered by FriendlyQnA
7

Answer:

6 (men) × 4 (days) = 24 units of work

• So, 12 (men) × [?] (days) = 24 units..

Hence, 24 ÷ 12 = 2 (days)

Answer:- (a) 2

hope this is helpful !