)If 64 men can do a job in 20 days, how many men will be needed to complete the work in 16 days.

Answers

Answered by brijeshayr
4

Answer:

80men

Step-by-step explanation:

64men=20days

x men=16days

(indirect propotion

64x20/16

1280/16

80 men

Answered by TooFree
3

Inverse proportion is the relationship between two variables such that the increase in one will cause a constant decrease in the other.

Given:

64 men = 20 days

Find the number of men needed to complete the work in 1 day:

20 days = 64 men

1 day = 64 x 20

1 day = 1280 men

Find the number of men needed to complete the work in 16 days:

1 day = 1280 men

16 days = 1280 ÷ 16

16 days = 80 men

Answer: 80 men