if 64 men can do a job in 20 days,how many men will be needed to complete the work in 16 days?
Answers
Answered by
4
Answer:
Step-by-step explanation:
This is the case of inverse proportion.
As, the no. of days required decrease the no. of men required will increase.
Let no. of men be x.
x = 64*20/16
x = 80