If 64 people complete a job in 48 days then how many people will complete tgKya same job in 16 days




Pls tell the answer its very urgent ​

Answers

Answered by brainyme2006
3

Answer:

HERE IS YOUR ANSWER

Step-by-step explanation:

PLEASE MARK AS BRAINLIEST AND FOLLOW ME....

Attachments:
Answered by JeanaShupp
3

192 people are required to complete the same job in 16 days

Step-by-step explanation:

Given :  64 people complete a job in 48 days

To find: people required to complete the same job in 16 days

People           64             x

Days              48           16

As the situation is inverse proportion

therefore

 64\times 48 = x\times 16 \\\\\Rightarrow x= \dfrac{64\times 48}{16} =192

Hence, we require 192 people to complete the same job in 16 days