If 64 people complete a job in 48 days then how many people will complete tgKya same job in 16 days
Pls tell the answer its very urgent
Answers
Answered by
3
Answer:
HERE IS YOUR ANSWER
Step-by-step explanation:
PLEASE MARK AS BRAINLIEST AND FOLLOW ME....
Attachments:
Answered by
3
192 people are required to complete the same job in 16 days
Step-by-step explanation:
Given : 64 people complete a job in 48 days
To find: people required to complete the same job in 16 days
People 64 x
Days 48 16
As the situation is inverse proportion
therefore
Hence, we require 192 people to complete the same job in 16 days