if 7 men and 5 boys can reap 168 hectares in 18 days how many days will 15men and 5boys take to reap 700 hectares one man being able to do 3 times as much as work of a boy............... no spamming pls spammers shall be reported
Answers
Answered by
2
Given :-
- (7M + 5B) can reap 168 hectares in 18days.
- One man being able to do 3 times as much as work of a boy.
To find :-
- In how many days will (15M+ 5B) take to reap 700 hectares.
Solution :-
Either we convert both data in men or in boys .
Lets convert In boys .
→ 1M = 3B (Efficiency)
→ 7M = 21B
→ 15M = 45B
So, Now, Question becomes ,
if (21B + 5B) = 26B can reap 168 hectares in 18 days , in how many days , (15M + 5B) = 50B will reap 700 hectares.
we know that,
→ B1 * D1 * W2 = B2 * D2 * W1 ( work is indirectly proportional) .
we have now :-
- B1 = 26 boys.
- D1 = 18 days.
- W1 = 168 hectares.
- B2 = 50B
- D2 = ? (we have to find.)
- W2 = 700 hectares.
(Reaping is work done here.)
So,
Putting all values now, we get :-
→ 26 * 18 * 700 = 50 * D2 * 168
→ 26 * 18 * 14 = D2 * 168
→ 26 * 18 = D2 * 12
→ 26 * 3 = D2 * 2
→ D2 = 13 * 3
→ D2 = 39 Days. (Ans.)