IF 70 men dig 15,000 sq m of a field in 5 days. find how many men will take to 2500 sq m field in 25 days

Answers

Answered by prantikskalitap8kpsj
4
In 5 days ------------------------ 70 men

In 1 day ------------------------- (70×5) men

15,000 m² -- in 1 day ---------------- (70×5) men

1 m² -- in 1 day ---------------------- {(70×5)/15,000} men

22,500 m² -- in 1 day ---------------{(70×5×22,500)/15,000} men

In 1 day -- 22,500 m² --------------- {(70×5×22,500)/15,000} men

In 25 days -- 22,500 m² -------------{(70×5×22,500)/15,000×25} men

∴ Total number of men required = (70×5×22,500)/15,000×25

                                                    = 3 men