if 78 men can do a work in 140 days then how many days can 42 men do the same work
Answers
Answered by
1
Answer:
The correct answer is 70 days
Step-by-step explanation:
mark me as brainlist
Answered by
5
if 78 men can do a work in 140 days then how many days can 42 men do the same work
42 mens can do piece of work in 140 / 78 × 42 = 980 / 13 = 75 upon 5/ 13 days .