if 8 men can dig a well in 18 days , in how days 12 men dig the same well
Answers
Answered by
0
5.3 days
as per my calculations
as per my calculations
Yash200529:
how
Answered by
7
FULL ANSWER WITH STEPS
Time taken by 8 men to dig a well = 18 days
Time taken by 1 man to dig a well = (18 × 8) days = 144 days
Here, instead of multiplication, I performed division, because if 1 man does the work, then the workload will be more.
Now,
Time taken by 12 men to dig a well = (144 ÷ 12) days = 12 days
Here, instead of multiplication, I performed division, because, instead of 1 man, if 12 men will do the whole work together, then the workload will reduce, and the work will be done much faster.
∴ In 12 days, 12 men can dig up the same well.
Hope this may help you.
If you have any doubt, then you can ask me in the comments.
Time taken by 8 men to dig a well = 18 days
Time taken by 1 man to dig a well = (18 × 8) days = 144 days
Here, instead of multiplication, I performed division, because if 1 man does the work, then the workload will be more.
Now,
Time taken by 12 men to dig a well = (144 ÷ 12) days = 12 days
Here, instead of multiplication, I performed division, because, instead of 1 man, if 12 men will do the whole work together, then the workload will reduce, and the work will be done much faster.
∴ In 12 days, 12 men can dig up the same well.
Hope this may help you.
If you have any doubt, then you can ask me in the comments.