Math, asked by subodh12, 1 year ago

if 8 men can do a piece of work in 15 days then in how many days will 20 men do the same work

Answers

Answered by Nikhil0204
1
X=8,20
Y=15,a
It is the case of inverse variation
X1×Y1=X2×Y2
8×20=15×a
160÷15=a
A=10.6days