if 8 persons can weave 160 shawls in 5 days , how many shawls will be woven by 3 persons in 14 days ?
Answers
Answered by
15
people 8:3
days:5:14
shawls 160:x
8×5×x=3×14×160
x=168
days:5:14
shawls 160:x
8×5×x=3×14×160
x=168