if 9 men and 12 women can do a piece of work in 4 days and 4 men and 16 women can do the same piece of work in 6 days.how long will 6 men and 24 women take to complete the same work?
Answers
Answered by
6
Form the expressions:
9 Men and 12 women do the work in 4 days:
9M + 12W = 4D
4 men and 16 women do the work in 6 days:
4M + 16W = 6D
.
Form the equations:
9M + 12W = 4D ------------------ [ 1 ]
4M + 16W = 6D ------------------ [ 2 ]
.
Since the work is the same:
(9 x 4)M + (12 x 4)W = (4 x 6)M + (16 x 6)W
.
Simplify and find M in term of W:
36M + 48W = 24M + 96W
36M - 24M = 96W - 48W
12M = 48W
1M = 4 W ------------------ [ 3 ]
.
Substitute 1M = 4W into [1] to find W:
9M + 12W = 4D
(9 x 4) W + 12W = 4D
36W + 12W = 4D
48W = 4D
1W = 4/48 D
1W = 1/12 D
.
Substitute 1W = 1/12D into [3] to find M:
1M = 4 W
1M = 4/12
1M = 1/3 D
.
.
Now find the days needed for 6 Men and 24 Women:
6M + 24W
= 6(1/3) + 24 (1/2)
= 2 + 2 = 4 days
.
Answer: 6 Men and 24 Women will need 4 days