if A and B can do a piece of work in 8 days and 12 days respectively, how many parts of the work do they work together in 4 days?
Answers
Answered by
2
Answer:
20 unit.
Step-by-step explanation:
so the total work done is = LCM (8,12)
= 24 unit
1 day work of A = 24/8 = 3 unit
1 day work of B = 24/12 = 2 unit
1 day work of
both (A+B) = 5 unit
so in 4 day they do a total of = 4*5 = 20 unit of work.