Math, asked by krishnendupro, 11 months ago

if a,b and c take 15,12and10 days respectively to complete a job.How many days will they need if they work on it together

Answers

Answered by Akshykumar
1
4 days . answer given by Raushan kumar this question is related to work time. so , easy questions is that
Attachments:

krishnendupro: thanks
krishnendupro: i actually wanted to check
krishnendupro: coz according to a site the answer is 6
Akshykumar: ok
krishnendupro: the. site is for prmo
Akshykumar: but on basis of questions answer is 4
Akshykumar: which school you read?