If A takes 6 days less than the time taken by B to finish a piece of work.If both A and B together can finish the work in 4 days.Find the time taken by B to finish the work?

Answers

Answered by vanshika2002
242
Hi friend,

Hope this helped u...
Attachments:
Answered by kavita9612
120
We call the time it takes for B to finish the piece of work x.

For problems like these, we must consider how much work can be done in one day.

1x+1x−6=14

x−6x(x−6)+xx(x−6)=14

4(x−6+x)=x2−6x

4(2x−6)=x2−6x

8x−24=x2−6x

0=x2−14x+24

0=(x−12)(x−2)

x=12and2

If the time it takes B is 2 days, then the time it takes A is −4 days, which has no sense.

Therefore, it would take B a period of 12 days to finish the job.

Hopefully this helps!