if aman and Sumit can do a job in 2 days Sumit and Kashish can do it in 4 days and aman and Kashish can do it in 12/5 days then find the number of days in which aman can do this job alone
Answers
Hope it helps you.....
Amar alone can work for 3 days
Step-by-step explanation:
Given:
If aman and Sumit can do a job in 2 days Sumit and Kashish can do it in 4 days and aman and Kashish can do it in days.
Then find the number of days in which aman can do this job alone.
Solution:
Let amar be a, sumit be s and kashish be k
a + s = ..(1)
s + k = …(2)
a + k = …(3)
Adding RHS of 1,2 and 3,
Total parts =
2 (a + s + k) =
A + s + k =
A =
Amar alone can work for 3 days
To know more:
A can finish a job alone in 42 days and C can do the same in 35 days. A and B both work on the project for 5 days, after which B leaves for vacation. A works for a day alone, after which C joins him and they both work together on the project for 8 days, after which A leaves for vacation. C works on the project alone for a day, after which B returns and both B and C together finish the project in 5 days. How long will it take for B to finish the project alone?
https://brainly.in/question/11825193
A can do a job alone in 24 days. B is 50% more efficient than A. Then B alone can finish the job in
A) 12 days
B) 18 days
C) 10 days
D) 16 days
https://brainly.in/question/5182877