Math, asked by roy869973, 5 months ago

If fakes 8 days for 12 men to construit a
wall. How many men should be put on one
Job If It is sequired to construcled in6 days​

Answers

Answered by janala
0

Answer:

16 days

Step-by-step explanation:

8 days-12 men

6 days-? men

inverse variation  

=8*12/6

=8*2

=16 days