if one man daily work 8 hour then complete 12 days.if he work daily 6 hour then how days complete work.
Answers
Answered by
5
Heya !!!
Given :---
A man do work for 8 hours and complete in 12 days.
If he work for 6 hours, then we have to find that in how many days he Wii complete the work.
As we know if he do work lesser, it will take more time.
So, this is a case of inverse Proportion........
In inverse proportion,
x1 ×y1 = x2 × y2.
So,
8 × 12 = 6 × y2
y2 = 96/6
y2 = 16.
Hence, he will take 16 days to complete the work.
Hope it helps
Given :---
A man do work for 8 hours and complete in 12 days.
If he work for 6 hours, then we have to find that in how many days he Wii complete the work.
As we know if he do work lesser, it will take more time.
So, this is a case of inverse Proportion........
In inverse proportion,
x1 ×y1 = x2 × y2.
So,
8 × 12 = 6 × y2
y2 = 96/6
y2 = 16.
Hence, he will take 16 days to complete the work.
Hope it helps