if P can complete a work in 30 days, Q can do the same work in 36 days, if they work together and after 5 days P leaves the work. Find in how many days Q will do the remaining work?​

Answers

Answered by shivamszar743
0

Answer:

Can complete a piece of work in 20 days and B can complete 20% of the work in 6 days if they work together in how many days can they finish 50% of the work if they work together?

Is able to do a piece of work in 15 days and Q can do the same work in 20 days if they can work together for 4 days what is the fraction of work left?

Can complete a work in 12 days working 8 hours a day Q can complete the same work in 8 days working 10 hours a day if both p and q work together working 8 hours a day in how many days?

Does a work in 10 days and B does the same work in 15 days in how many days they together will do the same work?

Answered by lathpiyush
0

Answer: 25 days

Step-by-step explanation: Amount of work P can do in 1 day = 1/30

Amount of work Q can do in 1 day = 1/36

Amount of work P and Q can do in 1 day = 1/30 + 1/36 = 11/180

Amount of work P and Q can together do in 5 days = 5 × (11/180) = 11/36

Fraction of work left = 1 – 11/36 = 25/36

Therefore Q finish remaining work (25/36) in 25