if rohan completes a work in 5 days and mohan completes the same work in 6 days then in what time the work will complete if they both work together?
Answers
Answered by
3
Answer: 30/11 Days
Step-by-step explanation: LCM of 5 and 6 = 30.
Let total no. of units of work = 30 units.
Thus A's one day work = 30/5 = 6 units.
B's one day work = 30/6 = 5 units.
There total one days work = 6+5 = 11 units.
Therefore 30 units will be completed in (30/11) days.