Math, asked by abhishekneg4, 5 months ago

If Suresh and Mahesh can do a work in 12 days Mahesh and Ramesh in15 days Suresh and Ramesh in 20 days How long will each of them take to complete work alone.

The right answer will be marked as brainliest ​

Answers

Answered by Anonymous
0

Answer:

The total time all of them take to complete the work is = 1/12+1/15+1/20 = 12/60

Step-by-step explanation:

Mahesh and suresh can do a work in =12days

mahesh and suresh 1 day work = 1/12

mahesh and ramesh can do work in = 15 days

their one day work= 1/15

suresh and ramesh can do work in = 20 days

their one day work =1/20

so, the total time all of them take to complete the work is = 1/12+1/15+1/20 = 12/60