if ten workes make a mashing in 30days then after five days five more worker came now in how many days they need to make mashin
yoy5:
thanks
Answers
Answered by
4
→Work of ten workers in one day= 1/30
→Work of ten workers in five days= 5/30
→Remaining work = 1-5/30
→(30-5)/30
→25/30
→Work of 15 workers in one day=15/30
They complete the work = 25/30÷15/30
→25/30*30/15
→5/3days
Thank you!!
Hope this will be helpful for you.
→Work of ten workers in five days= 5/30
→Remaining work = 1-5/30
→(30-5)/30
→25/30
→Work of 15 workers in one day=15/30
They complete the work = 25/30÷15/30
→25/30*30/15
→5/3days
Thank you!!
Hope this will be helpful for you.