if the hundred workers can finish the task in 50 days then how many days are required to finish the task by 25workers​

Answers

Answered by hritovash12
0

Explanation:

Hope this may help you

Have A nice day

Attachments:
Answered by iamrinadutta
0

hundred workers can finish the task in 50 days

1 worker can finish the task in 100/50

25 workers can finish the work in 100/50*25=50