if three firefighters can clean 240 metres of a fire trail in 2 days, how many metres of a fire trail can be cleared by 4 firefighters in three days, working at the same rate?

Answers

Answered by brunoconti
0

Answer:

Step-by-step explanation:

if Three firefighters can clear 240 meters of a fire trail in 2 days, then the Three firefighters can clear 120 meters of a fire trail in one Day, then each firefighter can clear 40 meters of a fire trail in one day, then one firefighter can clear 120 meters of a fire trail in 3 Days, then 4 firefighters can clear 480 meters of a fire trail in 3 Days.