If x man can do a pice of work in x days, than the number of days in which y man can do the same wrok is
Answers
Answered by
1
y/x days
X men complete work in x days
1 man " ". " 1/x days
Y men ". ". ". Y *1/x days =y/x days.
Hope it helps.