D) None of these.
45 more men will be required.
Step-by-step explanation:
number of persons working = 90
number of days required to complete = 40
Hence the work requirement = 90×40 = 3600 man-day
90 persons worked for 10 days, hence completed work = 90×10 = 900 man-day
Remaining work = 3600 - 900 = 2700 man-day
if remaining work has to be completed in another 20 days, then required persons = 2700 / 20 = 135.
Hence additional men required = 135 - 90 = 45 more men.