imran can finish a work in 10 days , Kamran is twice as efficient as Imran . If they work together , in how many days , the work will be finished ?
Answers
Answered by
1
Answer:
10/3 days the work will be finished
Step-by-step explanation:
time taken by imran = 10days then
kamran took 5 days
so
1/T = 1/5+1/10
1/T = 1+2/10
1/T = 3/10
T = 10/3
T is the total time taken by both imran and kamran to finish a work..
hope it works..