. In a company , 10 team members can complete a project in 3 months. If the project has to be completed in 2 months , how many team members should work on it ? *
Answers
Answer:
15 TEAM NUMBERS
EXPLANATION
IN A COMPANY 10 TEAM NUMBERS COMPLETE Ad PROJECT IN 3 MONTHS THEN THEY HAVE TO COMPLETE THE PROJECT IN 2 MONTHS. WE CAN TAKE 1 TEAM MEMBERS IS 5 MEMBERS 10 × 5 IS 50 MEMBERS THEN 15×5 IS 75.
MARK ME AS BRAINLIST.
Answer:
Here we should find how many team members should work to complete the project using the given data.
Final Answer: 15 team members can complete a project in 2 months.
Step-by-step explanation:
The given question has the concept of Inverse Proportion.
Inverse proportion:When one value increases and the other decreases.
Formula: × , where k is the constant.
From the given question,
- 10 team members can complete a project in 3 months
- team members should complete project in 2 months.It should be written as,
× ×
- Cancel 30 in the numerator and 2 in the denominator.That is,
team members
- Final Answer: 15 team members can complete a project in 2 months.