Math, asked by srinivaspasula64, 6 months ago

In a mixture of 48 kg concrete,the ratio of cement and sand is 5:3.write the equation between the cement and sand. draw a graph and find the quantity of cement in the mixture​

Answers

Answered by abhishekdalal0013
2

Answer:

As we know that during concreting when we place wet concrete , it gets harden after certain standard time( 30 mins IST & 10hrs FST), considering same it had be decided upon by Civil design Engineers to take a factor of safety ranging from 1.54 to 1.57 to counter that shrinkage.

i.e volume of dry Concrete = 1.54 to 1.57 times Volume of wet concrete.

Now calculations is as follows for 1cum(assumed) of Concrete work

ratio Sum = 1+1.5+3=5.5

Shrinkage or safety Factor =1.57 (you can take 1.54 also)

So Total volume of wet concrete required is :- 1.57cum

Volume of broken stone Require = (3/5.5) x 1.57 = 0.856 m3

Volume of sand Require = (1.5/5.5) x 1.57 = 0.471 m3

Volume of cement = (1/5.5) x 1.57 = 0.285 m3

= 0.285 x1440 = 411 kg

For 1m3 of M20 (1:1.5:3)

Broken stone = 0.856 m3

Sand = 0.472 m3

Cement = 8.22 bag.

Some important conclusion from above

8 bag of Cement is required for 1cum of concrete work in M20.

4.4 bag of cement is required for 1cum of concrete work in M10.

volume of dry concrete =1.54 times volume of wet concrete.

Answered by HEMANTD
4

Answer:

5x+3y=48(this is the equation)

Step-by-step explanation:

now, mark me BRAINLIEST. I am giving you the best answer possible.

values of x and y that suit the graph are,

  1. x=0, y=16
  2. x=3, y=11
  3. x=6, y=6

3 values are enough for ensuring a perfect graph.

mark me BRAINLIEST. I need it. I helped you better than anyone else.