Business Studies, asked by shivani8653, 3 months ago

* In an oil and gas project for which you are the project manager, you need to procure pipes. The laying of pipes into a trench is the
execution portion and the procurement activity needs to finish at the same time as the execution activity. So what is the relation of th
activities?
Select one:
Finish to Start
Start to Finish
Start to Start
Finish to Finish

Answers

Answered by DENISPARKER7
0

Answer:

the answer is start to finish

Explanation:

if you start a work you should finish so that's the answer...