Business Studies, asked by Ricky1034, 10 months ago

In order to produce a cost baseline, the project manager requires
1. Work packages, work breakdown, structure and project schedule
2. Cost estimates, work breakdown, structure and project schedule
3. Cost estimates, work packages, and project schedule
4. Cost estimates, work packages, and work breakdown structure

Answers

Answered by bolt783668
0

Answer:

2. Cost estimates, work breakdown, structure and project schedule

Explanation: