Math, asked by HamnaFarhan, 9 months ago

it takes 10 days for 12 men to complete a project if the project is to be completed 2 days earlier how many more Men should be employed in order to complete the project on time​

Answers

Answered by neil2008
2

14

If 10 days is required to to complete a project and requires 12 men

And it should be completed 2 days earlier means

10-2=8 so 12+2=14

So 14 people are required to do the project in 8 Days

Similar questions