it takes 10 days for 12 men to complete a project if the project is to be completed 2 days earlier how many more Men should be employed in order to complete the project on time
Answers
Answered by
2
14
If 10 days is required to to complete a project and requires 12 men
And it should be completed 2 days earlier means
10-2=8 so 12+2=14
So 14 people are required to do the project in 8 Days