Math, asked by gauri3190, 4 months ago

It takes 8 days for 12 men to construct a wall. How many men will be required to complete the construction in 6 days?​

Answers

Answered by pgarg964
2

8. x

12. 6

by cross multiply

12x=6*8

12x=48

x=48/12

x=4

4 men will take 6 days for completing construction