It takes 8 days for 12 men to construct a wall. How many men will be required to complete the construction in 6 days?
Answers
Answered by
2
8. x
12. 6
by cross multiply
12x=6*8
12x=48
x=48/12
x=4
4 men will take 6 days for completing construction