It takes 8 days for 12 men to construct a wall.How many men should be put on the job if it id requiredto be constructed in 6 days?
Answers
Answered by
0
Answer:
Number of men required to build the wall in 8 days = 12
So number of men required to build it in 6 days = 6*12/8 = 9 men