Keerthana completes her work in 24 days by working 5 hours a day.How many days will she take to complete the same work, working 8 hours a day?

Answers

Answered by TigerMan28
0

Answer:15 days

Step-by-step explanation:

Time taken=24×5/8

=120/8

=15