Kiran alone can do a piece of work in 15 days and aman can do the same work in 10 days if they start working together in how many days the work be completed
Answers
Answer:
6 days
Step-by-step explanation:
kiran = 15 days
Aman = 10 days
now take LCM = 30
so total work is 30 unit out of which Kiran can do 2 units of work per day while aman can do 3 unit work per day
it means they can do 5 unit work per day
time taken = total work/ efficiency
30/5 = 6 days
another formula is
X×Y/x+y
15×10/15+10
150/25=
6 days
✯Answer✯
❋Given
- Time taken by kiran for the work=15 days
- Time taken by Aman for the work= 10 days
❋To find
- Time taken by both together to complete the work.
❋Solution
✯So Final Answer✯
━━━━━━━━━━━━━━━━━━━━━━
✯Related Concept✯
❋ If A can do a piece of work in n days, then at a uniform rate of working A will finish 1/n th of work in 1 day.
❋If A can do n times faster than B, Then ratio of work done by A and B is n:1 and ratio of time taken by A and B is 1:n.
❋If A and B can do a work in X days and Y days respectively, then Time taken by both working together= XY/X+Y.
❋If a men and b women can do a picture of work in n days, then c men and d women can do the work in ( nab/bc+ad ) days.