Math, asked by kushi1020, 1 year ago

kushal and nainsuk while working together can complete a piece of work in 64 hours while nikhil alone can do it in 96 hours how long will khusal take​

Answers

Answered by choudhary3232
3

Kushal and nainsuk while working together can complete a piece of work in 64 hours while nikhil alone can do it in 96 hours how long will khusal take.


kushi1020: 87
choudhary3232: kya
choudhary3232: 87
Answered by wifilethbridge
3

Answer:

192 hours

Step-by-step explanation:

Kushal and Nikhil can do a part of work in 64 hours = 1

So, Kushal and Nikhil can do a part of work in 1 hour = \frac{1}{64}

Nikhil can do a part of work in 96 hours = 1

Nikhil can do a part of work in 1 hour = \frac{1}{96}

So, Kushal can do a part of work in 1 hour = \frac{1}{64}-\frac{1}{96}

                                                                     = \frac{1}{192}

Kushal can do complete work in 192 hours .

Hence Kushal can do complete work alone in 192 hours .