14. A, B and C can do a piece of work in 10 days; A alone can do it in 40 days and B alone can
do it in 30 days. In how many days will C alone do the same work?
Answers
Answered by
1
Step-by-step explanation:
given,
1) A, B and C can do a piece of work in 10 days
2) A alone can do it in 40 days
3) B alone can do it in 30 days.
let ,
one day work of A,B,C together = 1/10
one of work of A alone = 1/40
one day work of B alone = 1/30
one day work of C alone = 1/C
1/c = 1/10-1/40-1/30
1/c = 12-3-4/120
1/c = 12-7/120
1/c = 5/120 = 1/24
.: one day work done by C alone = 1/24
work done by C alone = 24days