time taken by the machine A,B and C together =
A work in 1min = 1/30
B work in 1min = 1/40
C work in 1min = 1/60
A+B+C=
1/30 + 1/40 + 1/60 = 9/120
In 1min they do 9/120 work
Total time taken to do this work =120/9min=13.33min