Math, asked by am9925481625, 8 months ago

Maitri and Aabhas do a work in 12 hours. Aabhas and Kavya do the work in 15 hours .Kavya and Maitri do the work in 20hours. In how many hours will they finish it together and sparately.​

Answers

Answered by ap4704879
1

Answer:

23.5 hours

together and sparately

Answered by dashaditya311
1

Work done by Maitri and Abhas in 1 hour = 1/12

Work done by Abhas and Kavya in 1 hour = 1/15

Work done by Kavya and Maitri in 1 hour = 1/20

Add the numbers

Maitri and Abhas + Abhas and Kavya + Kavya and Maitri=

1/12 + 1/15 + 1/20

=1/5

2(Maitri + Abhas + Kavya) = 1/5

Maitri + Abhas + Kavya = 1/5 × 1/2 = 1/10th of work in 1 day

Therefore, Maitri, Abhas and Kavya do the work together in 10 days.

Now add

Maitri and Abhas + Maitri and Kavya= 1/12 + 1/20 = 8/60

2(Maitri) + Kavya and Abhas

It is given that Kavya and Abhas do the work together in 15 hours.

So Subtract it from 8/60

8/60-1/15 = 4/60 = 1/15

1/15 × 1/2 = 1/30.

Maitri do the work in 30 hours

Do the same process for others.