(Marks:2)
6) If (5/8) of a piece of work is completed in (8/5) days, in how many days can rest of the work be completed?
O (5/8)
O (8/5)
O (24/25)
O (25/24)
Answers
Answered by
61
Given:
- (5/8) of a piece of work is completed in (8/5) days
To Find:
- how many days can rest of the work be completed?
Solution:
- Let's assume that the total part of work to be done is 1
Now,
- the work completed = 5/8 th part
The work left to be done =
- 1/1 - 5/8
- 8/8 - 5/8
- 3/5
Hence,
- 3/5 th part of the work is yet to be done,
Now,
- The time taken to complete 5/8 of work = 8/5 days
So,
- The time taken to complete 1/8th of the work will be
➱ 1/8 = 8/5 × 1/5
➱ 1/8 = 8/25 days
hence,
- 1/8th part oc the work will be done in 8/25 days
Now,
- We have to find the time taken complete 3/8 th part
➱ 8/25 × 3/1
➱ 24/25 days
Hence,
- Option c 24/25 is correct ✅
Thx for the question ♡!!
Answered by
113
Given:
- (5/8) th of a piece of work is completed in (8/5) days respectively
To Find:
- how many days can rest of the work be completed?
Solution:
- The remaining work can be done in 24/25 days
Full Solution:
Here,
- ↠Time Taken to do 5 / 8 th part of the work is 8/5 days
Now,
➼ Let's find the remaining part of the work to be completed respectively!
Considering,
↝The total part of the work to be done as 1
- ➱Let's find the remaining work to be done,
- Henceforth 3/8 th part of the work is yet to be completed!
➼ Now,
- ↠ let's find the time taken to complete 1/8th part of the work
➼ We know,
- 5/8 th work will be done in 8/5 days
So,
Now,
- We have to find in how many days will they complete 3/8 th part
Therefore:
- The time taken to complete the work is 24/25 days!!