Math, asked by arpit3795, 1 year ago

maths 8 class time and work icse

Answers

Answered by 860
2

Question 1: A can do a piece of work in 15 days while B can do it in 10 days. How long will they take together to do it?

Answer:

A’s 1 Day = \frac{1}{15}

B’s 1 Day work = \frac{1}{10}

A’s + B’s 1 Day work = (\frac{1}{15}+\frac{1}{10})=\ \frac{5}{30}=\ \frac{1}{6}

Therefore both can finish the work in 6 Days.

Question 2: A, B and C can do a piece of work in 12 days, 15 days and 10 days respectively. In what time will they all together finish it?

Answer:

A’s 1 Day = \frac{1}{12}

B’s 1 Day work = \frac{1}{15}

C’s 1 Day work = \frac{1}{10}

(A’s + B’s + C’s) 1 Day work = (\frac{1}{12} +\frac{1}{15} + \frac{1}{10}) = \frac{15}{60} = \frac{1}{4}

Therefore all three can finish the work in 4 Days.

Question 3: A and B together can do a piece of work in 35 days, while A alone can do it in 60 days. How long would B alone take to do it?

Answer:

A’s 1 Day = \frac{1}{60}

B’s 1 Day work = \frac{1}{x}

(A’s + B’s) 1 Day work = (\frac{1}{60} + \frac{1}{x} ) = \frac{1}{35}

Solving for x = 84 Days

Question 4: A can do a piece of work in 20 days while B can do it in 15 days. With the help of C, they finish the work in 5 days. In what time would C alone do it?

Answer:

A’s 1 Day = \frac{1}{20}

B’s 1 Day work = \frac{1}{15}

C’s 1 Day work = \frac{1}{x}

(A’s + B’s + C’s) 1 Day work = (\frac{1}{20} +\frac{1}{15} + \frac{1}{x} ) = \frac{1}{5}

Solving for x = 12 Days

Question 5: A can do a piece of work in 12 days and B alone can do it in 16 days. They worked together on it for 3 days and then A left. How long did B take to finish the remaining work?

Answer:

A’s 1 Day = \frac{1}{12}

B’s 1 Day work = \frac{1}{16}

(A’s + B’s) 1 Day work = (\frac{1}{12} +\frac{1}{16} ) = \frac{7}{48}

The amount of work that is completed in 3 days = \frac{3\times7}{48} = \frac{7}{16}

Amount of work left for B to complete = 1 - \frac{7}{16} = \frac{9}{16}

Therefore the number of days that B will take to finish the work = \frac {\frac{9}{16}} {\frac{1}{16} } = 9 days

Question 6: A can do \frac{1}{4} of a work in 5 days, while B can do \frac{1}{5} of the work in 6 days. In how many days can both do it together?

Answer:

If A can do \frac{1}{4} of a work in 5 days, then A can do the entire work in 20 days.

Therefore A’s 1 Day Work = \frac{1}{20}

If B can do \frac{1}{5} of a work in 6 days, then B can do the entire work in 30 days.

Therefore B’s 1 Day Work = \frac{1}{30}

(A’s + B’s) 1 Day work = (\frac{1}{20} +\frac{1}{30} ) = \frac{1}{12}

Therefore both can do the work in 12 days.

Question 7: A can dig a trench in 6 days while B can dig it in 8 days. They dug the trench working together and received 1120 for it. Find the share of each in it.

Answer:

A’s 1 Day = \frac{1}{6}

B’s 1 Day work = \frac{1}{8}

Therefore the ratio of work = \frac {\frac{1}{6}} {\frac{1}{8} } = \frac{8}{6}

Therefore A’s share = \frac{8}{14} \times 1120 = 640

Therefore B’s share = \frac{6}{14} \times 1120 = 480

Question 8: A can mow a field in 9 days; B can mow it in 12 days while C can mow it in 8 days. They all together mowed the field and received 1610 for it. How will the money be shared by them?

Answer:

A’s 1 Day = \frac{1}{9}

B’s 1 Day work = \frac{1}{12}

C’s 1 Day work = \frac{1}{18}

Therefore the ratio of their one day’s work = \frac{1}{9} \colon \frac{1}{12} \colon \frac{1}{18} = 8 \colon 6 \colon 9

Hence A’s share = \frac{8}{23} \times 1120 = 560

Hence A’s share = \frac{6}{23} \times 1120 = 420

Hence A’s share = \frac{9}{23} \times 1120 = 630



Answered by itzcutiepie009
0

Answer:

Question 1:

A can do a piece of work in

15 days while

B can do it in

10 days. How long will they take together to do it?

Answer:

A’s 1 Day

=

\frac{1}{15}

B’s 1 Day work

=

\frac{1}{10}

A’s + B’s 1 Day work =

(

\frac{1}{15}

+

\frac{1}{10}

)=

\frac{5}{30}

=

\frac{1}{6}

Therefore both can finish the work in 6 Days.

\\

Question 2:

A, B and

C can do a piece of work in

12 days,

15 days and

10 days respectively. In what time will they all together finish it?

Answer:

A’s 1 Day

=

\frac{1}{12}

B’s 1 Day work

=

\frac{1}{15}

C’s 1 Day work =

\frac{1}{10}

(A’s + B’s + C’s) 1 Day work

=

(

\frac{1}{12}

+

\frac{1}{15}

+

\frac{1}{10}

) =

\frac{15}{60}

=

\frac{1}{4}

Therefore all three can finish the work in 4 Days.

\\

Question 3:

A and

B together can do a piece of work in

35 days, while

A alone can do it in

60 days. How long would

B alone take to do it?

Answer:

A’s 1 Day

=

\frac{1}{60}

B’s 1 Day work

=

\frac{1}{x}

(A’s + B’s) 1 Day work

=

(

\frac{1}{60}

+

\frac{1}{x}

) =

\frac{1}{35}

Solving for

x = 84 Days

\\

Question 4:

A can do a piece of work in

20 days while

B can do it in

15 days. With the help of

C , they finish the work in

5 days. In what time would

C alone do it?

Answer:

A’s 1 Day

=

\frac{1}{20}

B’s 1 Day work

=

\frac{1}{15}

C’s 1 Day work

=

\frac{1}{x}

(A’s + B’s + C’s) 1 Day work

=

(\frac{1}{20}

+

\frac{1}{15}

+

\frac{1}{x}

) =

\frac{1}{5}

Solving for

x = 12 Days

\\

Question 5:

A can do a piece of work in

12 days and

B alone can do it in

16 days. They worked together on it for

3 days and then

A left. How long did

B take to finish the remaining work?

Answer:

A’s 1 Day

=

\frac{1}{12}

B’s 1 Day work

=

\frac{1}{16}

(A’s + B’s) 1 Day work

=

(

\frac{1}{12}

+

\frac{1}{16}

) =

\frac{7}{48}

The amount of work that is completed in 3 days

=

\frac{3\times7}{48}

=

\frac{7}{16}

Amount of work left for B to complete

=

1 -

\frac{7}{16}

=

\frac{9}{16}

Therefore the number of days that B will take to finish the work

=

\frac {\frac{9}{16}} {\frac{1}{16} } = 9 days

\\

Question 6:

A can do

\frac{1}{4} of a work in

5 days, while

B can do

\frac{1}{5} of the work in

6 days. In how many days can both do it together?

Answer:

If A can do

\frac{1}{4} of a work in

5 days, then A can do the entire work in

20 days.

Therefore A’s 1 Day Work

=

\frac{1}{20}

If B can do

\frac{1}{5} of a work in

6 days, then B can do the entire work in

30 days.

Therefore B’s 1 Day Work

=

\frac{1}{30}

(A’s + B’s) 1 Day work

=

(\frac{1}{20}

+

\frac{1}{30}

) =

\frac{1}{12}

Therefore both can do the work in

12 days.

\\

Question 7:

A can dig a trench in

6 days while

B can dig it in

8 days. They dug the trench working together and received

1120 for it. Find the share of each in it.

Answer:

A’s 1 Day

=

\frac{1}{6}

B’s 1 Day work

=

\frac{1}{8}

Therefore the ratio of work

=

\frac {\frac{1}{6}} {\frac{1}{8} } = \frac{8}{6}

Therefore A’s share

=

\frac{8}{14}

\times 1120 = 640

Therefore B’s share

=

\frac{6}{14}

\times 1120 = 480

\\

Question 8:

A can mow a field in

9 days;

B can mow it in

12 days while

C can mow it in

8 days. They all together mowed the field and received

1610 for it. How will the money be shared by them?

Answer:

A’s 1 Day

=

\frac{1}{9}

B’s 1 Day work

=

\frac{1}{12}

C’s 1 Day work

=

\frac{1}{18}

Therefore the ratio of their one day’s work

=

\frac{1}{9}

\colon

\frac{1}{12}

\colon

\frac{1}{18}

= 8 \colon 6 \colon 9

Hence A’s share

=

\frac{8}{23}

\times 1120 = 560

Hence A’s share

=

\frac{6}{23}

\times 1120 = 420

Hence A’s share

=

\frac{9}{23}

\times 1120 = 630

\\

Question 9:

A and

B can do a piece of work in

30 days;

B and

C in

24 days;

C and

A in

40 days. How long will it take them to do the work together? In what time can each finish it, working alone?

Answer:

(A’s + B’s) 1 Day work

=

\frac{1}{30}

(B’s + C’s) 1 Day work

=

\frac{1}{24}

(C’s + D’s) 1 Day work

=

\frac{1}{40}

Adding the above three

2\times(A + B + C) day work =

(\frac{1}{30}

+

\frac{1}{24}

+

\frac{1}{40}

) =

\frac{1}{10}

Therefore if they all work together, they will take 20 days to finish the work.

\\

Question 10:

A can do a piece of work in

80 days. He works at it for

10 days and then

B alone finishes the remaining work in

42 days. In how many days could both do it?

Answer:

A’s 1 Day

=

\frac{1}{80}

Work finished by A in 10 days

=

\frac{1}{80} \times

10 =

\frac{1}{8}

B finished the remainder of work

(1 -

\frac{1}{8}

) =

\frac{7}{8} in

42 days

Therefore 1 Days work for B

=

\frac{\frac{7}{8}}{42}

=

\frac{1}{48}

Hence B can do the work in 48 days

(A’s + B’s) 1 Day work

=

(

\frac{1}{80}

+

\frac{1}{48}

)=

\frac{1}{30}

Therefore both can do the work in 30 days.

Similar questions