Maths problem !!
1: takes 6 days less than to do the work . If both and working together can do it in 4 days , how many days will take to do it ?
Topic : Pair of linear equation in two variables !
→ Don't Spam
→ Nice answer = Brainliest
Answers
Answered by
14
⇒ x=12 or x = 2 x cannot be less than 6.
So x=12
Therefore,
B also can finish the work in 12 days.